The 15,000 PSI Hydrostatic Tube and Pipe testing mill sealing surface heads, at a major manufacture of pipe and tube, had become cracked. The surface of the fill and purge head blocks in the hydrotester require a fine, indication-free finish on the sealing surfaces. The surfaces had become cracked to such an extent that, while the testing machine could still maintain a 15,000 PSI hydrostatic test pressure, excessive amounts of water were being wasted during the test process. The material of the head blocks, AISI 4340 Nickel - Chrome - Moly, requires specialized weld media and pre and post weld heat treatment procedures in order to prevent cracking. During the preliminary client interview Furmanite learned that the prior vendor's repair was completed using local torch preheat only, standard carbon steel compatible electrodes and without post weld stress relief. Furmanite advised the client to be prepared for indications of discontinuity deeper than expected due to the uncontrolled processes previously used which we expected to be revealed after the initial pre-machining process.
Solution & Implementation
PT check during Pre-Machining
|
Post Weld Machining |
Heat Treatment
|
Furmanite offered an engineered six step controlled process as a solution, which was reviewed and accepted by the owner.
- Step one: An
On-Site machining clean up cut utilizing a Furmanite manufactured Silk® portable
facing machine of the 22" diameter sealing surface of the heads
commenced, with periodic PT until it was verified that all indications of
discontinuity (cracks) were removed. The pre-machining excavation depth
was roughly twice client expectations, due to the errant weld methods used
previously-certain indications were deep enough to require hand grinding,
to preserve as much parent metal as possible.
- Step two: The fill
and purge head blocks were preheated and the temperature held.
- Step three: The critical
22" diameter sealing surfaces of the heads were welded with the
proper low hydrogen electrodes, per weld procedure requirements.
Sufficient material was applied raising the sealing surface higher than
the OEM finish surface height.
- Step four: The
facing machine was repositioned to the datum points and the overlay of
weld was machined to a flatness tolerance 0.001" overall.
- Step five: The
sealing surfaces were honed to create a surface finish of 32 RMS, which
was required to satisfy the sealing criteria.
- Step six: The fill
and purge head blocks were post weld stress relieved and then ambient air
quenched.
![](http://ih.constantcontact.com/fs191/1116130639777/img/3.jpg)
I've been looking to get some help with on site machining for a project I'm doing. I'm helping my brother get a couple of excavators back up and running. There was an accident a few weeks ago and some of the machines were hit by a few rocks. http://www.fmt.com.au
ReplyDelete